New Construction

bus barn demolition

The Old Bus Barn is a Thing of the Past

Posted on: June 20, 2019

Over the last few weeks since school has been out, we have been able to remove the old bus barn.  This is necessary because it stood in the location where the new elementary school building will be built.   This is excited to continue seeing

read more …
garage door on a barn

Garage Doors Complete the Entryways

Posted on: May 24, 2019

The exterior garage doors for the bus barn were installed this week.  Additionally, the interior work continues as office, restroom, and storage spaces are laid out and framed.  We are expecting phase 1 of the construction project to be completed

read more …
garage door on a pole barn

Garage Doors Complete the Entryways

Posted on: May 24, 2019

The exterior garage doors for the bus barn were installed this week.  Additionally, the interior work continues as office, restroom, and storage spaces are laid out and framed.  We are expecting phase 1 of the construction project to be completed near the beginning of August.  

read more …
concrete being smoothed

Sidewalk Before and After

Posted on: May 16, 2019

It's always interesting to see before and after shots of a project.  While we plan to post the pictures when the bus barn is complete, we can see major steps along the way in the progress as finishing touches become complete.  Below you will see a

read more …
aerial shot of a new constuction

Aerial Images of the School's Property

Posted on: May 15, 2019

Thanks to the world of technology and the help of a local resident, parent, and community member, Jeremy Foley, we have been able to capture aerial shots of the barn construction zone.  Along with these images, there are overal school building pictures

read more …
new building progress

The Bus Barn Interior Work Begins

Posted on: May 1, 2019

Not only do we now have a roof on the new bus barn, but we also seeing interior work beginning.  

Also, traffic blockers/entrance protection barriers have been installed at the entrances of the building.  

read more …
new siding on a building

Several Pieces Working at Once

Posted on: April 4, 2019

This week at the construction site, we've seen several areas of progress that we want to share with you.  First, the siding has begun on the bus barn itself, along with furlim cross supports along the roof beams. There is also a trench that extends

read more …
stack of bricks

Masonry Work Along the Base of the New Barn

Posted on: March 29, 2019

While we were on Spring Break, construction continued and this week we saw a new group enter the scene...the masons.  Their expert masonry work has given a different look to the new structure as brick form the bottom half of the walls.   We've

read more …
roof beams of a construction

We Have Roof Beams!

Posted on: March 13, 2019

This week on the construction site of the new bus barn, we've seen the addition of roof beams with the use of equipment lifts.  

There's also been a fair amount of ground movement and things have gotten quite muddy in the surrounding areas.  

 

 

read more …
vertical beams of a new building

The New Structure Takes a Vertical Jump

Posted on: March 7, 2019

The new bus barn is getting easier to envision as we saw a few more changes this week. 

Vertical structure supports are put into place which will frame the new building.   

read more …

The Concrete Has Arrived

Posted on: March 1, 2019

As promised and right on time, the concrete trucks and concrete pump were busy pouring the foundation of the new bus barn today.   Once the concrete has set up, they will be covering the new floor with blankets to prevent freezing. The schedule

read more …
foundation of a new building

Prepping the Foundation

Posted on: February 28, 2019

From a distance, it looks like a pool of blue, but once up close, you see that the foundation is being prepped this week for a concrete pour on Friday.   The blue plastic sheets cover the sub-foundation, followed by mesh supports, and finally,

read more …
barn foundation

Electrical and Plumbing Foundation Work Begins

Posted on: February 22, 2019

Now that the footers have been poured and set, the next step is to lay the foundations for Electrical and Plumbing.  The contractors will revisit both electrical and plumbing several times before the project is complete because both pieces require

read more …
drill bits

Continued Soil Sampling

Posted on: February 21, 2019


Today, we saw some new equipment on the school property as a geotechnical engineering team continued pre-structural soil sampling.

 

read more …
constuction materials

Construction Materials are Delivered

Posted on: February 6, 2019

Update:  2-5-2019 Despite uncooperating weather these last few weeks, the footers have been poured for the new bus barn. The constuction materials have also been delivered and are currently lining the back parking lot right next to the construction

read more …