CONSTRUCTION UPDATE  10-14-2019


The new elementary building project begins.

The new elementary building has been divided into three segmented areas – Unit “A”, Unit “B” and Unit “C.”   Unit “A” is the side closest to the high school and contains the mechanicals, gymnasium and kitchen areas.   Unit “C” is the single story part of the building containing the early childhood wing closest to the present elementary.  Unit “B” is the core and classroom areas. 

The plan, weather permitting, is to focus on Area “A” first.  If weather was to become adverse, they will switch to Area “C” because it is one story and easier to get under roof.  Area “B” will always be the middle part of the work regardless. 

Area “A” milestones:

  • Drilled piers completed 10/21/19.
  • Start excavate and pour footers 10/22/2019 with a completion date of 11/11/19.
  • Early masonry work to start on 11/12/19.
  • Underground storm pipe, plumbing and electric for Unit “A” 11/7/19 to 11/21/19. 
  • Entire site excavation to grade completed by 10/14/19.